Jimcamel Posted August 10, 2021 Report Posted August 10, 2021 PTE AV Studio 10 - Mac 10.5.2 In the Timeline view, if I select the point between 2 slides and left-click and drag back and forth, the time for the TOTAL of those 2 slides does not change - it just shifts the time between the 2....and I can see this is useful for adjusting the start of the 2nd slide without messing up the rest of the timeline to the right.... But....what if I want to adjust the time such that the whole rest of the timeline to the right increases or decreases magnetically.....how do I do that without doing a Slide Options and typing in the requesting length? Quote
davegee Posted August 10, 2021 Report Posted August 10, 2021 Click in the slide timeline - just beyond the Slide Name? Quote
Jimcamel Posted August 16, 2021 Author Report Posted August 16, 2021 thanks - got it - I was hung up on doing it on the first slide - but as you suggested, it works fine. Quote
Recommended Posts
Join the conversation
You can post now and register later. If you have an account, sign in now to post with your account.